Water System Improvements

Water System & Seal Coat Improvements (E. 14th Street & Meadowlane)

The Water System Improvements program provides for replacing water mains in areas that are experiencing rusty water problems. It also provides for installing larger distribution mains. The Seal Coat Improvements program is the annual program for removal and replacement of built-up seal coat streets. Complete removal of built-up seal coat allows for repairs to curbs, gutters, and placement of new paving surfaces. 

Project Update2025-26 Water System Improvements Map.jpg

Weather permitting, water shut off will take place on Wednesday, November 26th. Anticipated shut off is 4 to 8 hours beginning at 8AM. 

You may/will experience a loss of water service for the duration noted above. Please refrain from attempting to use water during this time period. 

Should you have air or rust in your water from this work, try leaving the cold tap running for several minutes. This is typically all it takes to clear the water up. 

Project Schedule

Project will be starting in October 2025.

Project Contacts 

City of Ames Project Manager is Hafiz Ibrahim, he can be reached at 515-239-5245. 

City of Ames Inspector: Jesus Campa, he can be reached at 515-203-0797. 

Water System Improvements (Barr Drive, Douglas Ave, 17th Street)

The City of Ames has contracted with Iowa Water & Waste Systems to do water main improvements in your area. If unforeseen conditions don’t permit this work to be done on the above scheduled date, please anticipate it will take place on the next day. This work will involve a connection to the existing water main at the intersection of Barr Dr and Jensen Ave (South End).

Project Update

(6.25.26) 

25-26 Water System Improvements Construction Map 6.25.jpg

Weather permitting, starting Friday, June 26th, 
Iowa Water & Waste Systems will continue 
working on the water main improvements on Barr
Dr. The water main installation will be completed using
trenchless method; therefore, all driveway access will 
remain open during this phase. To facilitate the work, 
the contractor will temporary close two locations along
Barr Drive to complete excavation activities. Each
closure is expected to last one day, and the roadway
will be reopened to traffic by the end of the same day.
Further notices will be delivered as construction proceeds.

Action Required by Residents: Residents are encouraged
to utilize on-street parking when access to their driveway 
is not available. There are a few driveways that will need
to be temporarily closed during the water main
connection work. Those whose driveways will be blocked
will be notified. 

June 25 Construction Notice & Map(PDF, 7MB)

Project Schedule

The contractor is anticipating 8 to 10 weeks to complete 
this phase. Construction in your vicinity may not extend 
for this entire period.

Project Contacts 

City of Ames Project Manager is Hafiz Ibrahim, he can be reached at 515-239-5245. 

City of Ames Inspector: Jesus Campa, he can be reached at 515-203-0797. 

 

Water System & Seal Coat Improvements -Ferndale Ave

The Water System Improvements program provides for replacing water mains in areas that are experiencing rusty water problems. It also provides for installing larger distribution mains. The Seal Coat Improvements program is the annual program for removal and replacement of built-up seal coat streets. Complete removal of built-up seal coat allows for repairs to curbs, gutters, and placement of new paving surfaces.

Project Update

(7.2.26)   

Ferndale.jpg

Weather permitting, work will begin on Wednesday, July 
8th, 2026. Starting Wednesday July 8th, Manatt’s will 
begin pavement removal for Phase 1 on Ferndale 
Avenue. Following pavement removal, Iowa Water & 
Waste Systems will continue transferring water services 
for residents in phase 1 and will begin removing and 
replacing storm sewer and sanitary sewer structures. 
Phase 4 on Furman Drive will reopen to residents on 
Tuesday July 7th. Once the underground improvements 
are complete, Manatt’s will prepare the area for paving 
operations. Expect a full road closure on phase 1 
along Ferndale Avenue. Further notices will be delivered 
as construction proceeds.

Action Required by Residents: Residents within this phase 
will need to park on side streets starting Wednesday July 
8th at 7AM. The map shows the extents of work area.
Residents on this phase are encouraged to label their
trash and recycling containers with their addresses.
The contractor will move containers as needed for
collection and will return them afterward.

July 2 Construction Notice & Map(PDF, 9MB)

Project Schedule

The contractor is anticipating 6 weeks to complete Phase 1.

Project Contacts

City of Ames Project Manager is Hafiz Ibrahim, he can be reached at 515-239-5245. 

City of Ames Inspector: Jared Beckham, he can be reached at 515-203-0795.