Data Center Development Updates
The Ames City Council continues to evaluate data centers within City limits and is considering a broader analysis of policy for new development interested in Ames and the impact of that development on utilities, the environment, and quality of life concerns.
City staff have been asked staff to investigate 17 separate topics related to data centers. While this research is underway, the Council adopted a resolution for a temporary pause on processing any permits related to data centers until May 1, 2027.
At the next City Council meeting on Tuesday, Nov. 24, 2026, the Council will discuss options for developing zoning standards specific to data centers in Ames. There will be no final action taken at this meeting.
Data Center Zoning Options Staff Report - Nov. 24, 2026
The Resident Data Center Study Committee has been holding ongoing meetings and conducting their own research. For more information, visit their page.
Resident Data Center Study Committee
Project History: (2026)
- Sept. 22 - City Council Meeting: Council appointed Data Center Study Committee Members.
- Aug. 25 - City Council Meeting: Council approved the Data Center Study Committee Plan.
- Aug. 11 - City Council Meeting: Council Members discussed establishing a Data Center Study Committee.
- July 28 - City Council Meeting: Staff presented a report regarding a temporary delay in allowing data center developments.
- July 14 - City Council Meeting: Staff presented a memo outlining the legal means that the City Council has available to limit the construction of data centers. The memo contained options that relate to zoning, noise, and utility service.
- June 30 - Special City Council “Listening Session”: Residents had an opportunity to provide input and share comments regarding the proposal through small group interactions with City Council and City Staff.
- June 23 - City Council Meeting: Staff provided a general overview of the request. The City Council did not make any decisions and did not take public comment during this meeting.
- June 16 - A Staff Report was presented during Disposition of Communications to Council to highlight a proposal from Lightedge. City Council voted to place a Staff Report on the agenda for June 23 and a special resident listening session for June 30.
Lightedge Proposal
In spring 2026, the City received a request from Lightedge for a data center proposal. This began the community conversations around data center. The Lightedge proposal and any other data center is on hold while City staff and the community study the impacts of data centers.

The Airport Master Plan identifies that this area could be used for non-aeronautical uses.
The first phase of the project would result in 3 MW of electrical demand. The second phase would follow shortly and use 6 MW. Ultimate buildout would demand 25 MW. The time estimate of the full buildout is 10 years.