Ioway Creek at Brookside Project

grading below north bridge.jpg

 

After a slow start due to a rainy summer the contractor at Iowa Creek in Brookside has made significant progress this fall.

As of the end of November construction of the instream features and bank grading are nearing completion.

Native and temporary seeding has begun in some areas. Tree, shrub and final seeding is planned for Spring of 2026.