Ames Electric Department
Obtaining Utility
Services for New Construction
Utility
Service |
Temporary Electric Permit
Permanent Electric Meter |
Water Meter
| Yard Meter
Important
Numbers
Utility Customer Service Division
Inspections Division
Electric Meter Division
Electric Engineering Division |
515-239-5120
515-239-5153
515-239-5510
515-239-5175 |
Some forms on this page may be printed from
your personal computer. To view these publications electronically, use the Adobe® Acrobat® Reader
software. You may download the free version from Adobe's Web site and then download
our files to your computer.
- Complete a meter request form. A
meter request form may be printed
from here or obtained from the Inspections Division or the Utility customer Service
Division at 515 Clark Avenue. The completed form may be faxed to
515-239-5286. If the applicant is not an active customer on the Utility Billing System, a
separate application for utility service will be required. The applicant will be
contacted and an application for service will be mailed or faxed to the customer. A
deposit may also be required.
- Once the meter request form and, if required, the
application for utility service, is received by the Utility Customer Service Office, a
service order(s) is sent to the Electric and/or Water Meter Division to install the
meter(s). When you are ready for the meter(s), contact the appropriate division.
- After the meters have been installed, fees will be invoiced
by the respective meter division and billed through the Accounting Division of the Finance
Department.
- Charges for the utility consumption are billed by the
Utility Customer Service Division.
(return to list)
- The contractor or property owner must complete an
application for utility services. All utility services may be applied for on the same
form. The meter request form may
be obtained at the Inspection Division. To find out the current fee for temporary electric
service, call the Customer Service Division at 515-239-5120.
- Temporary services for construction shall be set within 2
feet on the back of the electric pedestal.
- Call the Electric Meter Division when ready to have the
meter set and the service connected. In most cases, service can be obtained the same day.
- The Electric Meter Division will set the temporary meter and
will connect the service.
(return to list)
- Obtain an electrical permit and
meter request form from the
Inspection Division at 515 Clark Avenue, 515-239-5153. The electrical permit must have the
signature of the electrical inspector before you proceed.
- Take the meter request form to the Electric Meter Division
at 2208 Edison and pick up the electric meter socket. The Electric Meter Division will
also determine the socket location on the building.
- Install the meter socket, service panel, GFCI and grounds.
- For residential homes and duplexes, provide a 30" deep
trench from the location of the meter socket to the transformer/secondary pedestal. For
commercial buildings, please refer to the electric meter standards available from the
Inspection Division. You must have the covers on the entrance panel and approval of the
electrical inspector or the meter will not be set.
- Call the Electric Meter Division for wire to be installed in
the trench and connected at the meter socket and transformer/secondary pedestal. Please
give us 3 days notice.
- Services above 200 Amps shall be referred to the Electric
Engineering Division at 502 Carroll.
(return to list)
Both the water meter and yard meter may be applied for on
the meter request form.